Service of Nissan Sunny from 1991 to 1997 release in n-14 body.
1. Maintenance instruction
2. Maintenance
3. Engines
3.1. 1,4 and 1,6 liters petrol engine
3.2. 2,0 liters petrol engine
3.3. Diesel engine
3.3.1. Technical characteristics
3.3.2. Gear belt
3.3.3. Replacement of laying of a head of cylinders
3.3.4. Valves
3.3.5. Replacement of maslootrazhatelny caps of a core of the valve
3.3.6. Check of the directing valves
3.3.7. Grinding in of a saddle of the valve
3.3.8. Processing of a head of cylinders / valves
3.3.9. Check / adjustment of gaps of valves
3.3.10. Check of a compression
3.3.11. Maple belt
3.3.12. Malfunctions of the engine
3.3.13. Engine lubrication system
3.3.14. Oil contour
3.3.15. Removal and installation of the pallet of a case
3.3.16. Oil pump
3.3.17. Cooling system
3.3.18. Injection device
3.3.19. Spark plugs
3.3.20. Power supply system
3.3.21. Check / replacement of the valve of interruption in supply of fuel
3.3.22. Speed of idling and maximum speed
3.3.23. Nozzles
3.3.24. Beginning of giving of the fuel pump of high pressure
3.3.25. Operation during the winter period
3.3.26. Specifications of a power supply system of the diesel
3.3.27. Useful tips for owners of the diesel car
4. Cooling system
5. System of heating and ventilation
6. Fuel and exhaust system
7. System of launch of the engine
8. Coupling
9. Transmissions
10. Half shafts
11. Brakes
12. Suspension brackets and steering
13. Body
14. Electric equipment
 









3-3-4-klapany.html

3.3.4. Valves

Removal

PERFORMANCE ORDER
1. Remove a head of cylinders.
2. Remove a cam-shaft.

Prevention

If old details of the distributive mechanism them are established it is necessary to establish on old places. Not to mix a detail, it is recommended to prepare the special place for an apportion of details.


3. Take out dish-shaped pushers and spread out them according to adjusting situation.
4. Remove springs of valves. For removal of conic crackers and at the same time valves with springs use the special grabber of springs of valves.
5. Squeeze springs of valves and take out conic crackers.
6. Weaken and remove the grabber of valves.
7. Take out the valve.
8. Take out the top plate of springs, springs and the lower plates of springs.
9. Remove maslootrazhatelny caps of cores of valves.

Installation

PERFORMANCE ORDER
1. If are established old the valve and an old head of cylinders, before assembly check guides of valves.
2. If new valves are installed in an old head, it is necessary to process saddles of valves in a head of cylinders and to make grinding in of valves.
3. Clear valves of the deposit remains by means of a shaber and a wire brush.
4. Oil all dish-shaped pushers engine and insert into the corresponding openings.
5. Establish ravpredvat.
6. Replace laying of a head of cylinders, establish a head of cylinders.
7. If it is required, adjust a gap of valves.


3.3.3. Replacement of laying of a head of cylinders

3.3.5. Replacement of maslootrazhatelny caps of a core of the valve